www.simpsonanchors.com


SET High Strength Epoxy-Tie® Anchoring Adhesive

Load Adjustment Factors in Face of Wall Installation

in 8" Grout-Filled CMU:

End / Edge Distance and Spacing, Tension and Shear Loads

 

How to use these charts:

  1. The following tables are for reduced End and Edge Distance and Spacing.
  2. Locate the anchor size to be used for either a tension and/or
    shear load application.
  3. Locate the embedment (E) at which the anchor is to be installed.
  4. Locate the end or edge distance (Cact) or spacing (Sact) at which the
    anchor is to be installed.
  5. The load adjustment factor (fc or fs) is the intersection of the row and column.
  6. Multiply the allowable load by the applicable load adjustment factor.
  7. Reduction factors for multiple edges or spacing are multiplied together.
  8. Adjustment factors do not apply to allowable steel strength values.
  9. Adjustment factors are to be applied to allowable Tension or Shear Load
    Based on CMU Strength
    values only.
Tension Load Concrete Block (CMU)
End Distance Tension (fc)

Edge Distance Tension
Tension Load Concrete Block (CMU)
Edge Distance Tension (fc)

End Distance Tension

**The allowable tension load reduction factor is permitted to equal 1.0 provided both of the following conditions are met: (a) The anchor is installed with a minimum end distance, Cmin, between 4 inches and 8 inches; and (b) a masonry return wall of identical construction is on the opposite side (such as two masonry walls intersecting at a building corner).
  1. E = Embedment depth (inches).
  2. Cact = actual end or edge distance at which anchor is installed (inches).
  3. Ccr = critical end or edge distance for 100% load (inches).
  4. Cmin = minimum end or edge distance for reduced load (inches).
  5. fc = adjustment factor for allowable load at actual end or edge distance.
  6. fccr = adjustment factor for allowable load at critical end or edge distance. fccr is always = 1.00.
  7. fcmin = adjustment factor for allowable load at minimum end or edge distance.
  8. fc = fcmin + [(1 - fcmin) (Cact - Cmin) / (Ccr - Cmin)].

Tension Load Concrete Block (CMU)
End and Edge Distance Shear (fc)
Shear Load Perpendicular
to End or Edge

End and Edge Distance Shear
Tension Load Concrete Block (CMU)
End and Edge Distance Shear (fc)
Shear Load Parallel
to End or Edge

End and Edge Distance Shear

  1. E = Embedment depth (inches).
  2. Cact = actual end or edge distance at which anchor is installed (inches).
  3. Ccr = critical end or edge distance for 100% load (inches).
  4. Cmin = minimum end or edge distance for reduced load (inches).
  5. fc = adjustment factor for allowable load at actual end or edge distance.
  6. fccr = adjustment factor for allowable load at critical end or edge distance. fccr is always = 1.00.
  7. fcmin = adjustment factor for allowable load at minimum end or edge distance.
  8. fc = fcmin + [(1 - fcmin) (Cact - Cmin) / (Ccr - Cmin)].

Tension Load Concrete Block (CMU)
Spacing Tension (fs)

Spacing Tension
Tension Load Concrete Block (CMU)
Spacing Shear (fs)

Spacing Shear

  1. E = Embedment depth (inches).
  2. Sact = actual spacing distance at which anchors are installed (inches).
  3. Scr = critical spacing distance for 100% load (inches).
  4. Smin = minimum spacing distance for reduced load (inches).
  5. fs = adjustment factor for allowable load at actual spacing distance.
  6. fscr = adjustment factor for allowable load at critical spacing distance. fscr is always = 1.00.
  7. fsmin = adjustment factor for allowable load at minimum spacing distance.
  8. fs = fsmin + [(1 - fsmin) (Sact - Smin) / (Scr - Smin)].

Printed from
© 2008 Simpson Strong-Tie®